Ajnara sports city villas
completion would have two stages, first completion of structure work and second
finishing of the completed structure. We have discussed completion of structure
work in last post. Let’s have an insight of finishing of the completed
structure.
As
structure of the building reach up to fourth floor, engineers start the brick
work. This process of brick work move towards upper floors as structure moves
towards completion. It takes three months to complete brick work on all floors.
After completing brick work the work on inside and outside walls plaster
starts. Plaster work would be completed within two months of brick work
completion. This whole process is directly linked with providing painters base
for starting paint and tiling work of building.
Internal
fittings and fixtures like wardrobes, modular cabinets, fall ceiling, door
fittings take three months and along with it engineers would install sanitary
wares in washrooms. Electric fitting like geyser, fans, tube lights, air
conditioners, switches, electric plugs and chimney and hob would be done in 15
to days. Rest work like painting the inside and outside walls would further
take two to three months. Paint work would be done very carefully and would be
having many coats. These all parts would complete the finishing of ajnara sports city villas.
In
conclusion we can say that after completion the structure work of ajnara sports
city villas in initial two years, finishing work would take next one and half
years. So ajnara group would give possession of ajnara sports city villas in three and half years.